Pavement Repair and Resurfacing Works – Mount Cotton Road, Mount Cotton

Pavement repair and resurfacing works Mount Cotton Road, Mount Cotton

Update: October 2024

The Department of Transport and Main Roads (TMR) advises that pavement repair and resurfacing works will be undertaken in both directions on Mount Cotton Road between Hillview Road and Seaview Road, Mount Cotton.

These works are being undertaken as part of TMR’s maintenance program to improve the road surface and enhance road safety for all road users.

Work activities

  • Removal and replacement of asphalt.
  • Reinstatement of temporary line marking.
  • Final line marking.

Timing

  • Works are scheduled to commence late October 2024 and are expected to take approximately two weeks to complete, weather and construction conditions permitting.
  • Typical construction hours will be from 8pm to 5am, Sunday to Friday. Night works are required for road user safety and to avoid what would otherwise be extensive traffic queuing and disruption to the road network.
  • While the majority of the works will be undertaken at night, some Saturday or other out of hours works during the day may be required.
  • Final line marking works to improve the reflectivity and longevity of the road line marking will be applied approximately six weeks after the completion of road resurfacing to allow for adequate curing.

Expected impacts

  • Temporary changed traffic conditions: Temporary traffic changes include, road shoulder and lane closures, roadworks speed limit reductions and short- term traffic disruptions. Please allow extra time when planning your travel and follow the directions of roadside signage and traffic controllers.
  • Temporary construction noise: Nearby residents and businesses may experience a short term increase in noise, dust, and odour during the works. Reversing beepers and flashing lights will be used on vehicles for safety.

On completion, TMR officers will continue to review the site for up to three months. During this time TMR will assess the work undertaken for longevity and quality. In some cases, TMR may need to request further work at the location to rectify any defects.

Every effort will be made to minimise impacts on the local community and surrounds.

TMR appreciates your patience and cooperation while these important works are carried out.

Original: October 2023

Pavement repair and resurfacing works Mount Cotton Road, Mount Cotton

The Department of Transport and Main Roads (TMR) will be conducting pavement repair and resurfacing works in both directions on Mount Cotton Road between Hillview Road and Lakeside Drive, Mount Cotton.

These works are being undertaken as part of TMR’s routine maintenance program to improve the road surface and enhance road safety for all road users.

Work activities

  • Removal and replacement of asphalt.
  • Reinstatement of line marking and final line marking.

Timing

  • Works will commence early October 2023 and are expected to take approximately three weeks to complete, weather and site conditions permitting.
  • Typical construction hours will be from 8pm to 5am, Sunday to Friday. Night works are required for road user safety and to avoid what would otherwise be extensive traffic queuing and disruption to the road network. While the majority of work will be at night, some Saturday or other out of hours works may be required.
  • Final line marking will be applied approximately six weeks after the completion of road resurfacing to allow for adequate curing.

Expected impacts

  • Changed traffic conditions: Temporary traffic changes include road shoulder and lane closures, traffic detours, roadworks speed limit reductions and short-term traffic disruptions. Please allow extra time when planning your travel and follow the directions of roadside signage and traffic controllers.
  • Temporary construction noise: Reversing beepers and flashing lights will be used for safety. Machinery will be in use and for a short time, nearby residents and businesses can expect some increased noise, dust and odour.

On completion, TMR officers will continue to review the site for up to three months. During this time TMR will assess the work undertaken for longevity and quality. In some cases, TMR may need to request further work at the location to rectify any defects.

Every effort will be made to minimise impacts on the local community and surrounds. TMR appreciates your patience and cooperation while these important works are carried out.

  • 00

    days

  • 00

    hours

  • 00

    minutes

  • 00

    seconds

Date

20 Oct 2024 - 01 Nov 2024

Time

8:00 pm - 5:00 am
Category

Organizer

Department of Transport and Main Roads
Phone
13 19 40
Website
http://www.qldtraffic.qld.gov.au